A containerized nitrogen generator is a complete gas plant pre-installed inside a 20- or 40-foot ISO container: compressor, dryer, PSA towers, buffer tank, control system and utilities, wired and pipe-tested before shipping. It arrives on a truck, sits on level ground, and makes gas within days. For mines, oilfields, construction sites, remote plants and anyone without a spare machine room, it removes the single biggest project risk: site works.
What Ships Inside the Box
- Air system: screw compressor, refrigerant dryer, multi-stage filtration, air receiver
- PSA module: twin adsorption towers with carbon molecular sieve, switching valves, purity analyzer
- Nitrogen side: buffer tank, pressure regulation, optional booster to 1.5–3.0 MPa
- Control & safety: PLC with HMI panel, remote-monitoring module, gas and fire detection options
- Container: insulated and ventilated, lighting, service doors, lift points, optional ATEX or climate packages
Typical Capacity Ranges
| Container | Capacity range | Typical purity | Best fit |
|---|---|---|---|
| 20 ft | 5–60 Nm³/h | 95–99.99% | Laser shops, food plants, mining sites |
| 40 ft | 60–300 Nm³/h | 95–99.9% | Oilfield EOR, pipelines, glass & steel |
| Multi-container | 300–2000+ Nm³/h | per project | Major EOR and industrial projects |
Because units run in parallel, capacity is modular: two 40-ft containers deliver N+1 redundancy for continuous processes that cannot tolerate gas interruptions.
Containerized vs Traditional Plant Room
| Containerized | Plant-room install | |
|---|---|---|
| Civil works | Level ground only | Building, foundations, HVAC |
| Time to first gas | 2–5 days after arrival | 4–12 weeks of site works |
| Relocation | Lift and move | Not practical |
| Weather protection | Built in (−40 °C / +50 °C options) | Depends on building |
| Capex | +30–60% vs skid | Lower equipment, higher project cost |
Deployment: What Actually Happens
- Weeks 1–2: sizing review and electrical interface confirmed — power feed, nitrogen outlet point, drain and vent positions.
- Weeks 3–10: container build and factory acceptance test, including witnessed purity and dew-point run.
- Shipping: standard container freight to any port or inland site.
- Days 1–3 on site: offload, set level, connect power and outlet, commission. Operator training takes half a day.